Which of the following is an important part of the change request process for which the administrator still must plan in this situation?
A network administrator wants to schedule a major OS upgrade for the router that serves as an organization's default gateway. The administrator has documented the purpose of the change, scoped the change, and done a thorough risk analysis.
A
Document a backout plan to roll back changes to the router