A critical group of experts in a project team expressed their concerns over recent cost estimates produced with their project manager. They insisted that they hadn't considered enough alternatives. However, they are just in the early stage of the project life cycle. Which of the following is a valid tool or technique that can aid the project manager in addressing the team’s concerns?
A
Data analysis.
explanation
Data analysis, which is a tool and technique of the Estimate Costs process, includes several techniques, such as alternatives analysis, reserve analysis and cost of quality.