A customer requested new requirements to be incorporated midway through the delivery of development services. However, the customer refused to submit a change request to modify the terms of the contract and insisted that the changes be implemented at no cost. Neither party changed their stance on the situation after multiple discussions. What technique should be used to address this situation?
A
Claims administration.
explanation
Claims administration is a tool and technique of the Control Procurements process that addresses contested changes between the buyer and seller, which may then convert into a claim.