A product owner requests the Scrum master to show the remaining work effort for the sprint. What will be shown to the product owner?

A A burndown chart.
explanation

The time remaining for the sprint, the time period of the sprint on the horizontal axis, and the backlog items on the vertical axis are displayed in a burndown chart.