Question:

A project has some changes in performance, and some risks have occurred. As a result, EAC and BAC have changed as well. The project's manager is being asked for an estimate of the cost of the project at completion. Which of the following statements is correct?

A BAC may no longer be reasonable given the changes in performance, so you should use EAC to forecast the cost at completion.
explanation

The question is asking for an estimate at completion, not an estimate to complete. On a project, when changes in performance or risks occur, it may cause BAC to no longer make sense. When that is the case, switch to the EAC to project the cost at completion.