Question:

A project manager creates an official team charter while establishing a new project team. Select two things the project manager will include within the document.

A Team values.
explanation

A project manager uses the team charter to establish the team, clarify expectations, and create team norms. It includes team values, agreements, and how the team will operate together throughout the project’s life, team ground rules and other expected behaviors.