A project manager develops his project charter and uses a hybrid project management approach. Almost immediately, he finds several constraints. Where will he document these constraints and update the change regularly throughout the project?
A
Assumption log.
explanation
The assumption log, which is first created during the Develop Project Charter process, contains both assumptions and constraints.