A project manager has a weekly meeting with the project sponsor. Due to the company's rocky performance, the sponsor nervously asks about the chances of the project ending successfully. The project has been on track to date and is nearing the end of the Execution phase. What should the project manager's response be?

A The likelihood of successful completion is high.
explanation

During the Executing phase, the chances of successful completion are medium to high. The likelihood of success is high since the project is nearing the end of execution and is currently on track.