A project manager has just found out that three functional managers, who are highly interested in the project, heavily influence on the allocation of enterprise resources. Therefore, the manager updates her salience model and considers how it affects the project. What activity is the project manager engaged in?

A Stakeholder analysis.
explanation

The project manager is conducting the Identify Stakeholders process and stakeholder analysis is performed as part of this process. Stakeholder analysis and identification should be done regularly throughout the project.