Question:
The Milestone list provides information on the completion date of major project deliverables. It is a project document that identifies all project milestones and indicates the date on which each milestone is expected to be achieved. The milestones may include the completion of major project deliverables, the achievement of key project objectives, or important project events.
The Schedule baseline, on the other hand, is a project document that contains the approved project schedule, including start and finish dates for all project activities and milestones. The baseline is used as a basis for comparison to track and monitor project progress.
The Milestone report is a summary of the status of all project milestones and their completion dates. It is typically used to communicate project progress to stakeholders.
The Final report is a comprehensive summary of the entire project, including its objectives, scope, deliverables, outcomes, and lessons learned. It is typically prepared at the end of the project and is used to communicate the project results to stakeholders. While the final report may contain information on the completion date of major project deliverables, it is not the primary source of this information.
Comments