Question:

A project manager is performing activities related to monitoring and controlling the project's scope. What key information can this manager use in conjunction with the plan to help his activities get started?

A Work performance data.
explanation

The project manager will need to measure completed scope against planned scope. To do this, he will need work with performance data, a key input of the Control Scope process. Variance and trend analysis are not the inputs of the process, but are its tools and techniques.