Question:

A project manager is supervising the execution of the team’s project activities. At the end of a day, she was satisfied that her team had been working together harmoniously and beginning to adjust their work habits and behaviors to support the other. The team is currently in what stage of Tuckman team development ladder?

A Norming.
explanation

In the norming stage, the team members have gained mutual understanding and are focused on confronting project concerns versus each other.