Question:

A project manager is taking into consideration the skills and capabilities needed to accomplish planned outcomes of a project. These skills and capabilities include the type and quantities of material, equipment, and supplies. Which of the following activities is the project manager engaged in?

A Estimating resource needs.
explanation

The project manager is conducting the activities related to the Estimate Activity Resources process.