Question:

A project manager started the activities to develop the project's schedule. By now, he has generated the schedule management plan and led the team through a decomposition of work packages into activities. Now, he and his team are arranging activities. He plans to visualize the gathered information by a network diagram during the next meeting. What network diagramming method is most likely to be used?

A Precedence diagramming method.
explanation

Precedence diagramming method (PDM) or activity on node (AON) are among the most common diagramming methods. PDM uses boxes to represent activities and arrows to connect the activities and show the dependencies between them.