Question:

A project manager collaborates with the project team to identify lessons learned, which will be documented and summarized in the project's final report. What activity is this?

A Administrative closure.
explanation

While information captured will be added to the lessons learned register, administrative closure captures additional activities, such as archiving information and creating the final report.