Question:

A project sponsor is asking for a forecast of the possible cost to complete the project work. Which of the following statements is TRUE regarding this situation?

A You’ll use the ETC calculation, which is part of the forecasting tool and technique of the Control Costs process.
explanation

The question refers to the estimate to complete (ETC) calculation, which will estimate the project's remaining work. This calculation is also a part of the forecasting tool and technique of the Control Costs process.