Question:

A project team gathered together after having successfully completed a project. At the end of this meeting, the project manager concluded with a celebration for the successful achievement of the project's final feature and completion of all transition activities. Post-meeting, this manager sat down to summarize the project’s journey, including its performance against planned business value and objectives.Then the summary document, which would be archived the remaining project artifacts for future reference, was handed over to the sponsors. What is this document called?

A Final report.
explanation

The final report is an output of the completion of all activities associated with the Close Project or Phase process. This project artifact summarizes the project performance or phase and generally captures the following:
- Summary description of the project or phase.
- Performance against scope/quality/cost/schedule objectives.
- Summary of validation information about the work completed.
- Summary of risks or issues encountered.
- Summary of whether the end result produced by the project satisfies the business needs that the project was addressing.