Question:

A project team has recently participated in a working session to determine the costs associated with individual activities. They broke each activity down into smaller chunks to conduct a more accurate estimate. What estimating technique is being used by this team?

A Bottom-up estimating.
explanation

Bottom-up estimating technique estimates costs associated with every activity individually and then rolls them up to obtain either a more accurate activity-level estimate or a total project estimate.