Question:

A project team has recently participated in a working session to examine and document the effectiveness of risk responses in dealing with overall project risk. They have been performing what project management process?

A Monitor Risks.
explanation

The Monitor Risks process is supposed to monitor risk response plans, track identified risks, identify and analyze new risks, and evaluate the effectiveness of the risk processes. Risk review meetings, as part of conducting this process, may be held to examine and document the effectiveness of risk responses in dealing with overall project risks and individual project risks.