A risk manager met with the project manager to discuss the project's progress. The risk manager expressed concerns about the feedback, indicating that the team is unlikely to meet their go-live date. What should the project manager do?

A Submit a change request in the form of preventive action.
explanation

The project manager should take preventive actions since an issue has not yet occurred. Preventive actions are submitted through a change request, then evaluated and dispositioned by the project's change control board.