Question:
The stakeholder management plan, which is created out of the Plan Stakeholder Management process, captures and identifies the needed strategies for effectively engaging stakeholders. This plan is based on the stakeholder analysis completed as part of creating the stakeholder register. While the project management plan is not the best answer because a more specific option is available.