After a face-to-face meeting, an issue has been resolved and you have come away with an update to the issue log, change requests, project management plan updates, and project documents updates. Finally, a change request have been submitted. Which of the following statements is NOT true about the situation?
A
This describes the Manage Communications process.
explanation
All of the provided options are the outputs of the Manage Stakeholder Engagement process, in which the issue log is used more like an action item log.