After conducting a lessons learned session at the end of each project phase, the project manager's responsibilities are collecting feedback from the team and creating a process improvement plan. Which of the following options is NOT included in the process improvement plan?

A Failure rate.
explanation

The process improvement plan contains 4 primary items: process boundaries, process configuration, process metrics, and targets for improved performance.