As an employee of Writer’s Block, a service that reviews and critiques manuscripts for aspiring writers, you were assigned to manage a project regarding a new computer system. This system is used to log, track, and save submitted manuscripts along with the editor’s notes. You hired and worked with a vendor who wrote the system from scratch to your specifications. You are reviewing a report about certain aspects of the project’s performance, and one of the measurements on the report is the expected cost of the work when completed. What does this measurement describe?
A
EAC
explanation
Estimate At Completion (EAC) refers to the expected cost of the work when it is completed.