Question:

Sue, as the head of an enterprise PMO, has been granted a significant level of authority within the company. Project managers directly report to the PMO. Which best describes the type of PMO that Sue leads?

A Directive.
explanation

Directive PMOs typically exert direct control over and manage projects. They possess a high degree of control over projects and assign project managers. Additionally, project managers report directly to the PMO.