At the end of each quarter, the PMO of a company performs a review focusing on measuring the project team’s effectiveness. This type of activity can best be described as _________.

A Team performance assessments.
explanation

While project performance appraisals are feedback given directly to project team members, team performance assessments, whose purpose is to increase the team’s performance, are an output of the Develop Project Team process.