Question:

Availability, cost, and ability are examples of _________.

A Team member selection criteria.
explanation

During a team building process, several factors must be taken into account by the project managers. Multi-criteria decision analysis is used as a tool in the decision-making process. Availability, cost, and ability are some of the team member selection criteria that a project manager can use. Availability, cost, and ability may be assumptions or constraints captured but are not considered ongoing.