Question:

In the final meeting of a project, the project manager rallied the team together to wrap up the project with a celebration for the successful achievement of the final feature. During this meeting, the project manager captured feedback from the team about what had gone well and what could have been improved throughout the project’s life. The achievement of planned benefits were also discussed. In what project artifact will this information be captured?

A Lessons learned register.
explanation

The lessons learned register is commonly generated in the early stage of a project and updated at various points throughout the project. A final lessons learned session, which takes place at the end of a project, is held to capture information for future reference.