Question:

In the Planning stage of your project, you have just started taking the activities related to the Determine Budget process. Along with the cost baseline, what is the other possible output of this activity?

A Project funding requirements.
explanation

The possible outputs of the Determine Budget process include: the cost baseline, project funding requirements, and updates to project documents. Particularly, the project funding requirements capture the total funding requirements and periodic funding requirements of the project.