In the Planning stage of your project, you have just started to generate the cost baseline. As a project manager, what activity are you involved in?

A Performing the Determine Budget process.
explanation

In this case, you are taking the Determine Budget process whose purpose is to aggregate the estimated costs of each activity or work packages. Therefore, you can establish an authorized cost baseline.