header bg

Scan QR code or get instant email to install app

Question:

Is this statement true or false?
Due to sunk costs, premature closure of a project phase managed by an Adaptive approach is more likely to experience failure compared to a project managed by a Predictive approach.

A This is a false statement.
explanation

Projects using an Adaptive approach prioritize work depending on the highest business value items. Early benefits realization reduces the failure of premature closure due to sunk costs.

Related Information

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *

*