Is this statement true or false?
Due to sunk costs, premature closure of a project phase managed by an Adaptive approach is more likely to experience failure compared to a project managed by a Predictive approach.
A
This is a false statement.
explanation
Projects using an Adaptive approach prioritize work depending on the highest business value items. Early benefits realization reduces the failure of premature closure due to sunk costs.