Question:

Katrira is a senior project manager for a company that is developing a new product. She has just finished overseeing several planned risk responses' implementation. What is the next activity which she should perform?

A Risk audit.
explanation

The Implement Risk Responses process has just been finished and the next activities which should be carried out, are those associated with the Monitor Risks process. Risk audits are a tool and technique used to evaluate the effectiveness of risk responses that have been implemented, and typically occur either through risk review meetings or through dedicated risk audit meetings.