Kaylee - a risk manager, works with Alyssa - a project manager for a top healthcare company. After analyzing risk, they noted that 5 of the 20 identified risks were deemed to be low priority. Where will they document these risks?

A A watch list.
explanation

In the risk register, low-priority risks are added to a watch list, where they will be monitored for possible changes.