Question:

Kaylee is a project manager for a company that builds software for mobile devices. One of her projects is to develop a health app that syncs with other health apps to combine and analyze the data for a comprehensive view. To prepare for the upcoming iteration, she works with the project team to complete a review of the project’s prioritized backlog. What should she do when knowing that several features of the app may be affected by a new regulation passed by the government?

A Assess the impact of the new regulation on the project’s scope and update the backlog to reflect the necessary changes.
explanation

Project managers need to be aware of changes occurring across the business landscape to understand the impact of their projects. When this happens, it is advisable for project managers to assess and prioritize the impacts of these changes on their project and then adjust their project back-log accordingly.

Related Information

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *

*