On a meeting with his sponsor to review and obtain feedback on the project’s benefits management plan, John carefully reviewed the following information: - The list of benefits captured to date. - The owners of each benefit. - How they map to the company’s strategic objectives. What feedback about the plan is the sponsor likely to give to John?
A
The benefits management plan is lacking a system that will ensure benefits are tracked.
explanation
John’s benefits management plan lacks the implementation of a system whose function is to track and measure benefits in order to ensure that value is achieved as expected.