Question:

On a project, a stakeholder tells the project manager that the schedule must be adjusted to finish one week sooner than previously planned. If this project is managed in a predictive approach, what would be the preferred approach for the project manager to take in order to make the change happen?

A Fast-track the schedule.
explanation

That the project manager has told the scheduler to compress the schedule by one week means one of two schedule compression techniques: crashing or fast-tracking will be used. The lower-cost option, which is fast tracking, should be prioritized .