Sue is an enterprise project manager for Burger Queen. She is operating the implementation of an enterprise relationship management system. This system uses waterfall in combination with Scrum. To prepare for a meeting with the sponsor, Sue plans to review her team's work load and if they will finish on time. Which of the following are useful point-in-time measurements that Sue may use?

A Burnup chart.
explanation

Burnup charts, burndown charts, lead time, and cycle time are the useful in-the-moment measurements, which provide insight into capacity and predictability measures. The team can get an idea of their work load and whether they will finish on time with these types of measurements.