Question:

That the project team has had to remake an unqualified deliverable has resulted in a one-week schedule delay, in addition to the cost of rework. This is an example of _________.

A Poor quality.
explanation

Quality also looks to remove waste and non-value-added processes as well as improve processes along with making sure that project requirements are being met.