header bg

Scan QR code or get instant email to install app

Question:

The project sponsor has reviewed the initial project schedule you created and is unhappy because the project end date does not align with the promised date given to the customer. In response, you decide to employ some compression techniques. Choose a CORRECT statement about duration compression.

A Schedule compression shortens the project schedule but doesn’t change the project scope.
explanation

Schedule compression techniques are employed to accelerate the project schedule and reduce the overall duration without altering the project scope. The aim is to complete the project in a shorter period of time while still delivering the planned scope of work.