Question:

The new PMO director in the project management office that you work at has adjusted project assignments to accommodate a large strategic project. You meet with the previous project manager of your new project to review stakeholder communication requirements, escalation processes, and the list of project-related meetings. What document will provide you with this information?

A Communications management plan.
explanation

The communications management plan is a subsidiary of the project management plan. While project management plan is also correct, the communications management plan is more specific. The communications management plan contains stakeholder communication requirements, escalation processes, and methods for receiving/obtaining information.