Question:

There is a new issue that occurs during the execution phase of a project. What is the first thing that the project manager should do in response?

A Note the issue within an issue log.
explanation

The project manager should note the issue within the issue log first; therefore an owner can then be assigned to the issue, and a target resolution date could be set. This will also allow for a more structured and documented resolution.