These processes adjust stakeholder engagement and communication strategies and plans; these adjustments must be based on how the project is progressing and how the results compare to the plan. What are these processes?

A Monitor Communications and Monitor Stakeholder Engagement.
explanation

The Monitor Communications and Monitor Stakeholder Engagement process are described in the question. Both of these assess the results of communication and stakeholder engagement activities then compare them against the desired outcomes. Changes to these activities may be made based on the comparison.