Question:

This table displays a small sample of a project’s critical path. Only when an activity has finished can the next activity begin. What is the late start and late finish date for activity No.3?

image
A Late start is 5/29, and late finish is 6/4.
explanation

To calculate the late finish, subtracting the duration of the last activity (activity 4) from its start date. Because it is one day, it means the late finish is 6/4. Late start is 7 days before 6/4, which is 5/29.