Using a predictive approach to managing projects, you have completed your cost baseline. You are now working on determining funding requirements. Choose a correct statement.
A
Management reserves are the difference between the funding requirements and the cost baseline.
explanation
Management reserve is released in increments throughout the project. The funding requirements, an output of the Determine Budget process, are derived from the cost baseline.