Question:

What is a characteristic of the Planning process group?

A Stakeholder influence is high.
explanation

During the Planning phase of the project life cycle, stakeholder has the tendency to highly influence on the project (it is highest during Initiating phase). On the other hand, costs, staffing, and chances for successful project completion tend to be low during Planning phase.