Question:

What is an individual project risk?

A An uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives.
explanation

As noted by the PMBOKĀ® Guide, individual project risk and overall project risk are two levels of risk. An uncertain event or condition that has a positive or negative effect on one or more project objectives, if it occurs, is an individual project risk.