Question:

What is the likely output of quantitative risk analysis?

A An assessment of overall project risk exposure.
explanation

The risk register is updated as part of the Perform Quantitative Risk Analysis process. An assessment of overall project risk exposure and detailed probabilistic analysis of the project are included in these updates.