Question:

What strategy is being described in the following situation?
A project manager is working on a pharmaceutical project whose activities aiming at producing the deliverables are now being planned out in detail. Then the rest tasks will be planned at higher levels until the testing results show the additional product details.

A Rolling wave planning.
explanation

The principle of the "rolling wave planning" technique is to plan out the near work detailedly, and then plan out the future work at higher levels of the WBS. Although "rolling wave planning" seems to be a form of progressive elaboration, it is on a more specific level. While progressive elaboration and rolling wave planning are planned and controlled, scope creep is not.