Question:

What tangible result is produced when a project manager conducts quantitative risk analysis?

A An assessment of overall project risk exposure.
explanation

As part of the Perform Quantitative Risk Analysis process, updates are made to the risk register, which involve an assessment of the overall project risk exposure and detailed probabilistic analysis of the project.