Question:

What type of contract should a project manager use when managing a project on a hybrid approach?

A Master service agreement.
explanation

A master service agreement allows procurement team and the project manager to create a multi-tiered structure when formalizing a contracting relationship. This type of contract is especially useful for hybrid project approaches, where some items will be fixed (i.e., warranties) and others will be more dynamic.